Anticipated Construction Schedule for the Week of March 12th
Monday 03/12/18
Crew will be excavating the Tunneling pit (crossing under Austin Blvd.) in Parking lot 25F
FOR THE RESIDENTS USING PARKING 25F PLEASE BE SURE TO HAVE YOUR VEHICLES MOVED BY 7:00AM MONDAY
Tuesday 03/13/18
Continue with the Tunneling pit (crossing under Austin Blvd.) in Parking lot 25F
Wednesday 03/14/18
Continue with the Tunneling pit (crossing under Austin Blvd.) in Parking lot 25F
Thursday 03/15/18
Mobilize tunneling Equipment in Parking lot 25F
Friday 03/16/18
Begin Tunneling Procedures
TO AVOID GETTING A TICKET BE SURE TO DISPLAY YOUR ORANGE TEMPORARY PARKING PASS IN THE INSIDE REAR WINDOW IN LOWER LEFT-HAND CORNER (DRIVER’S SIDE).
ANY QUESTIONS PLEASE CONTACT JOHN KUEBRICH AT 630-878-2356